Residence Hall Capital Plan (as of 6/24/09)

Res Hall Project

Design

Bids Open

Construct

Perry/Briggs/Harmon/Gordon Integrated & Addressable Fire System

01/07 - 12/07

01/08

Summer 2009

Thompson Full Rehab (172 beds)

11/07 - 02/09

03/09

05/09 - 08/10

MacVicar Renovation & Roof Replacement (197 beds)

07/08 - 11/09

02/10

Summer 2010 & 01/11 - 08/11

McLean Elevator

07/08 - 11/09

02/10

Summer 2010

Lower Quad Site Improvements

07/08 - 11/09

02/10

Summer 2011

McFarlane & McLean Roofs

01/11 - 11/11

12/11

Summer 2012

High Rise Window Replacement

01/11 - 11/11

12/11

Summers 2012/13

Benedict/Dobson Full Renovations
09/11 - 11/12
01/13
2013 - 2014
Harmon/Gordon Full Renovations
09/13 - 11/14
01/15
2015 - 2016
High Rise Renovations
TBD
TBD
TBD
Town Homes Phase II
TBD
TBD
TBD