Res Hall Project |
Design |
Bids Open |
Construct |
Perry/Briggs/Harmon/Gordon Integrated & Addressable Fire System |
01/07 - 12/07 |
01/08 |
Summer 2009 |
Thompson Full Rehab (172 beds) |
11/07 - 02/09 |
03/09 |
05/09 - 08/10 |
MacVicar Renovation & Roof Replacement (197 beds) |
07/08 - 11/09 |
02/10 |
Summer 2010 & 01/11 - 08/11 |
McLean Elevator |
07/08 - 11/09 |
02/10 |
Summer 2010 |
Lower Quad Site Improvements |
07/08 - 11/09 |
02/10 |
Summer 2011 |
McFarlane & McLean Roofs |
01/11 - 11/11 |
12/11 |
Summer 2012 |
High Rise Window Replacement |
01/11 - 11/11 |
12/11 |
Summers 2012/13 |
| Benedict/Dobson Full Renovations | 09/11 - 11/12 |
01/13 |
2013 - 2014 |
| Harmon/Gordon Full Renovations | 09/13 - 11/14 |
01/15 |
2015 - 2016 |
| High Rise Renovations | TBD |
TBD |
TBD |
| Town Homes Phase II | TBD |
TBD |
TBD |